RES (Wind Power Plant): Installation and Permits

1 Mayıs 2026 Energy and Environmental Law 1 dk okuma 68 görüntülenme

RES (Wind Power Plant) projects require more complex permit processes than SPP.

Process

  1. Wind measurement campaign (1-2 years)
  2. Turbine location and capacity determination
  3. EMDK pre-license application
  4. Air traffic permit (DHMI, TSK)
  5. Ornithology (bird migration route) report
  6. EIA process
  7. Grid connection permit (TEİAŞ)
  8. Zoning process
  9. Construction
  10. Commissioning

Permitting Institutions

  • EMRA (license)
  • DHMİ (air traffic)
  • TSK (military compliance)
  • Ministry of Environment (EIA)
  • Agriculture Ministry (forest/agricultural land)
  • Relevant municipality (zoning)

Environmental Impacts

  • Bird migration route obstructions
  • Noise
  • Visual impact
  • Soil change

YEKDEM Support

  • Like other renewable resources
  • USD based price guarantee
  • Domestic turbine additional incentive

Off-Shore RES

  • Wind power plant on the sea
  • It is still in its early stages in Türkiye
  • Areas such as Marmara and the Black Sea are potential

Council of State 14th Chamber

14. The Department accepts that "environmental protection" and "energy production need" should be balanced in WPP investments, and that investments may be prevented in critical areas such as bird migration routes.

Energy law lawyer is recommended.

Telif bildirimi This content and all related Q&A texts are protected under Turkish Copyright Law No. 5846. Unauthorized copying, reproduction, publication, adaptation, bulk extraction, or commercial use is prohibited; legal and criminal remedies are reserved in case of infringement.

Hukuki destek arıyorsanız

Bu konuda profesyonel hukuki destek için Aycan Ceylan Avukatlık Bürosu olarak yanınızdayız.

Görüşme Planla